10.40 - TIME BUDGET
Objective
The objective of this document is to assist you in preparing the audit budget at planning stage and subsequently comparing it to actual results.
Document placement
Document 10.40 – Time budget can be found in the Pre-engagement planning folder in the Caseware document manager.

Document content
This document is designed to be a worksheet type document with space for recording the planned and actual time spent on the audit sections, for each team member.
Before completing this document, you must set up users in Caseware.
This is done in Protection Setup.
Refer to the guidance in Collaboration – Set protection.
Layout
COLUMN
|
INPUT REQUIRED
|
OUTCOME
|
Insert row
|
Click on the icon to add another row for the section.
|
No impact on the engagement file.
|
Delete row
|
This functionality is only available after extra rows have been added.
Click on the icon to remove the extra row.
|
No impact on the engagement file.
|
Responsible person
|
Select the responsible person from the drop-down box. This will only work once users have been set up correctly in Caseware as explained above.
|
No impact on the engagement file.
|
Detail
|
No input required in this column. The full name of the person appears based on the responsible person selected.
|
No impact on the engagement file.
|
Rate
|
No input required in this column. The hourly rate for the responsible person, as set up in Caseware protection setup, displays here.
|
No impact on the engagement file.
|
Planned Units
|
Record the number of hours planned to perform the procedures.
|
No impact on the engagement file.
|
Planned Cost
|
No input required in this column. The cost is automatically calculated by Rate x Planned Units
|
No impact on the engagement file.
|
Actual Units
|
Record the number of hours spent when the procedures were performed.
|
No impact on the engagement file.
|
Actual Cost
|
No input required in this column. The actual cost is automatically calculated by Rate x Actual Units.
|
No impact on the engagement file.
|
Document outcomes
After completing the input fields the difference between planned and actual cost is automatically calculated and can be used for further analysis.
Group audits
There is no additional content specifically related to group audits.
Features
The following features are available in the document:
• Freeze, see page F17
Rate this article:
|vote=None|
Processing...
(Popularity = 1/100, Rating = 0.0/5)
Related Articles
Probe Audit | 10.40 Time budget
Probe Audit | What is Probe Audit Premium+ ?
Probe | Pre-Engagement Planning - 10.40 Time Budget
Probe Audit Premium+ | What's New
view all...
Search Results
Sending a Future Dated Request
Can I request for a future "As of Date"?
Can I request more information from the Responder (Bank)?
I can’t request authorisation from a client signer as the name is greyed out (cannot be selected)?
Probe | How do I fix the error “knowledge library not found” when inserting a step in the work program?
view all...