Confirmation.com - IA Engagement | Planning – 165 Risk And Control Matrix (RACM)

Notice: We have upgraded to the New Gen Confirmation platform. Clients may experience login issues. Please contact support for assistance.

FAQ

IA Engagement | Planning – 165 Risk And Control Matrix (RACM)

Published:  06/05/2026

How do I identify and assess risks within an engagement, link them to controls, and determine whether those controls reduce risk to an acceptable level?


  Instructions:

The Risk and control matrix (RACM) is used to document and assess the relationship between objectives, risks, and controls within the activity under review. It enables auditors to evaluate the level of risk before and after controls are applied by determining inherent and residual risk. By linking risks to controls and assessing control efficiency, the RACM provides a structured foundation for a risk-based audit approach and supports the development of audit procedures and conclusions.

Objective

To ensure that all significant risks are identified, appropriately assessed, and supported by effective controls, enabling a risk-based audit approach and informed audit conclusions.

Page position

Planning | 165 Risk and control matrix can be found within 130 Understanding and risk assessment on the Planning page.

 

Page content

The RACM consists of five main tabs:

Objectives Tab

  • Capture activity objectives.
  • Each objective represents a desired outcome of the process.
  • Risks will be linked to these objectives.

To add an objective, select the + sign, which will add a line. Simply typing the objective in the relevant line will add an objective to the list.

Risks Tab

Capture identified risks related to the achievement of the activity objectives.

To add a risk, select the + button. A dialog will open requiring the user to choose between a Risk, Control or Findings / Recommendations. Choose Risk.

 

 

Selecting Risk will open the following screen that requires the user to complete the initial details of the risk.

 

Initial fields for completion include:

  • Title
  • Description (cause, event, impact)
  • Level (overall or objective-specific)
  • Type (normal, significant, fraud)
  • Activity objectives (Only if objective specific)
  • References (If other areas of the engagement need to be referenced)

When all relevant fields have been completed, the Save button becomes available for selection.

Note: Newly added risks will only be visible when the page is refreshed.

Note: The risk assessment is not complete at this stage.

The user must select the edit button in order to complete the assessment of the specific risk, or make changes to the initial assessment. Additional fields available for completion are:

  • Likelihood
  • Impact
  • Inherent Risk (The system calculates inherent risk automatically)
  • Controls (if no controls have been identified yet, they can be created in the next step).

When all relevant fields have been completed or required amendments made, select Save.

Controls Tab

Capture controls linked to risks.

To add a CONTROL, select the + button. A dialog will open requiring the user to choose between a Risk, Control or Findings / Recommendations. Choose Control.

Selecting Control will open the following screen that requires the user to complete the initial details of the control.

 

Initial fields for completion include:

  • Title
  • Brief Description
  • Risks (Risks can be linked at a later stage)
  • Frequency (How often the control works)
  • Execution (manual or automated)
  • Classification (e.g., preventative)
  • Key control indicator (yes or no)

When all relevant fields have been completed, the Save button becomes available for selection.

Note: The control is not complete at this stage. A prompt will appear for a short while in the bottom right-hand corner, which will open up the control for completion or further editing. If the prompt is not selected, the page will need to be refreshed for the control to appear on this page.

The user must select the edit button  in order to complete the details of the control, or make changes to the initial control description and selections. Additional fields available for completion are:

  • Linking a risk
  • Classification (Preventative or detective)
  • Adequacy of control (Satisfactory or Unsatisfactory)
  • Design reference (link to another part of the working papers)
  • Test this control (only available if the adequacy is satisfactory)
  • Control is effective (only available if the adequacy is satisfactory)
  • Evaluation reference (link to another part of the working papers)
  • Notes on control testing (any additional notes)

When all relevant fields have been completed or required amendments made, select Save.

 

Matrix Tab

Displays a consolidated view of the risks with the following fields:

  • Likelihood
  • Impact
  • Inherent risk
  • Control efficiency
  • Residual risk

The user needs to manually configure the control effectiveness by selecting the edit button that will open up the following dialog.

Residual risk is automatically calculated based on control efficiency.

The user must select Save for any changes to be saved to the overall Matrix.

Guidance Tab

Provides definitions and explanations of:

  • Objectives
  • Risks
  • Controls
  • Matrix
  • Risk scoring methodology

This guidance is synced to the IA Governance App.

How to Complete

Define objectives

Identify what the process is intended to achieve.

Identify risks

Capture risks that could prevent objectives from being achieved.

Ensure risks include cause, event, and impact.

Assess inherent risk

Assign likelihood and impact.

Confirm system-calculated inherent risk.

Document controls

Link controls to risks.

Ensure controls are clearly described and relevant.

Assess controls

Evaluate adequacy and effectiveness.

Identify key controls.

Determine control efficiency

Apply judgement where multiple controls exist.

Review residual risk

Confirm whether risk is reduced to an acceptable level.

Page outcomes

Using the Send Notification Letter query ensures that stakeholders formally acknowledge the engagement before it begins, while all communication, responses, and supporting documentation are centrally recorded. This strengthens audit traceability, improves communication efficiency, and ensures readiness for the next phase of the engagement.

Features

The following features are available on this page:

  • Queries
 
Rate this article: 
  (Popularity = 0/100, Rating = 0.0/5)

   Related Articles

Probe Audit | Planning Risk Assessment | 11.50 Information system and control activities Probe | In 12.20, why is my inherent, fraud and control risk at financial statement level assessment showing "blank" or "Not yet assessed"? Probe | Planning Risk Assessment | 11.50 Information system and control activities Probe Methodology | Planning Risk Assessment - 11.20 Inherent Risk Assessment view all...


   Search Results

What if the Account ID requested was closed for the As of Date (New Version of Confirmation) Closed Account Confirmation for Bank Users What do I do if I can't locate the Account ID or Client Name requested? (New Version of Confirmation) Close a Caseware Cloud account How do I add / modify / remove flip account settings? view all...



Didn't find what you were looking for?


Watch a video

Check out our helpful video guides

Contact Support

Contact our support team
Copyright © 2026 | All Rights Reserved